Construction Of Major Br. No. 62,115,131 in connection with Anugul - Sukinda New BG Line Project
Project image not available
COMPLETED
PROJECT DETAILS
Girder works — 11 x 45.7M OWG.
Girder work scope: 11 x 45.7M OWG. Executed for agency: M/s. Woodhill Hillways JV. Completed: 62- 04.10.2019 115- 25.03.2021 131- 16/18.03.2021.
Remarks: Complete
Technical Information
| Status | Completed |
|---|---|
| Project Type | Railway Bridge |
| Client / Agency | M/s. Woodhill Hillways JV |
| LOA / Reference | RVNL/BBS/EW-MB/19-47 KM./ANGL-SKND/01 Dtd: 23-04-2014 |
| Date of Completion | 62- 04.10.2019 115- 25.03.2021 131- 16/18.03.2021 |
| Girder / Work Type | Open Web Girder |
| Span / Quantity | 11 x 45.7M OWG |
| Weight | 1551 MT |