Construction of 3rd & 4th line between Jarapada – Talcher Road “ Execution of Major Bridge No. 359 (1x60.0m Camel Back Girder), 361 (1x60.0m Camel Back Girder), 363 (1x60.0m Camel Back Girder) in connection with with 3rd & 4th Line of Jarapada-Budhapank Project and between Angul & Balram including yards of MCRL inner Corridor Phase-I Doubling.

IN PROGRESS

PROJECT DETAILS

Girder works in progress — 3 x 60.0m CBG.

Girder work scope: 3 x 60.0m CBG. Location: Angul. Executed for agency: M/s K K Engineering & Construction Pvt Ltd.

Remarks: Work in Progress

Technical Information

Status Ongoing / In Progress
Project Type Railway Bridge
Client / Agency M/s K K Engineering & Construction Pvt Ltd
Location Angul
LOA / Reference RVNL/BBS/Bidding/SLT/Execution 3rd & 4th line/Maj. Bridge/JRPD-TLHD/Pkg-2/25/195/3404, Dated 07-05-2025.
Girder / Work Type Camel Back Girder
Span / Quantity 3 x 60.0m CBG